Please note that all dates, job lengths and manpower requirements are all estimates and are subject to change without notice. 

Work Outlook Area 1- Mark Wertz & Paul Easley - Business Agents

Ongoing - Severstal Stove Project - 10 to 12 a shift, 6/10's for six weeks.  Metro is the contractor.  Should wrap up in March 2012.

March 20, 2012 - DTE Trenton Channel  Annual on Unit 9 - roughly 10 to 12 per shift for about two weeks.  URS is the contractor.

April 16, 2012 - DTE St. Clair Outage - approximately 40 boilermakers, one shift, 5/10's for about seven weeks.  URS is the contractor.

September 11, 2012 - DTE Belle River Outage - approximately 120 per shift for about 8 to 10 weeks.  Monarch is the contractor.

October 2012 - BOP - 40 panel change out, 40 to 50 a shift for roughly 28 days.  Monarch is the contractor.

There will be short work as it comes in.

(back to top)

 

Work Outlook Area 2- Jim Kaffenberger, Business Agent

March 19, 2012: DC Cook refueling outage - 30 days of 6/12's; 25 Boilermakers; in processing starts March 5, 2012

 

April 8, 2012: Palisades refueling outage - 30 days of 6/12's for five Boilermakers; in processing starts March 30, 2012

 

April 2, 2012: JH Campbell Unit 3 - 30 days of 6/10's for 40 Boilermakers; Northern Boiler is the contractor and will be working on the boiler, expansion joints, ld fans and precipitator

 

April 2, 2012 - JH Campbell Unit 3 - 30 day SCR Outage (hours and manpower tbd); Enerfab will remove two rows of catalyst and reinstall three rows.

(back to top)

Work Outlook Area 3 - Mike Card, Business Agent

MCV - January 2012 - C Inspection, 12 Boilermakers, 6/10's, two to three weeks, AP Com

Weadock 8 Outage - March 2012 - nine days, more details to come

Karn 3 - April 2012 - 46 days, more details to come

Karn 4 - May 2012 - ten days, more details to come

Short work as it comes in.

(back to top)

Work Outlook Area 4 - Jim Calouette, Business Agent

Abbotts Field training for New Page:  http://www.abbottsfield.com/newpage-escanaba-contractor-safety/

Verso paper on line training:  http://visitor.versopapertraining.com/olenet/student/default.aspx?parms=1

Verso registration code - QUINNCON

February 2012: Day & Zimmerman Unit 8 at WE Energies Presque Isle plant. Three weeks , 40 hours,  for 4 - 6 men

March 9, 2012:  Day & Zimmerman Unit 7 at WE Energies Presque Isle plant. 8 – 9 weeks, 6 – 10’s, 45 men days, 45 men nights. Set-up will start the end of February 2012

New Page – Escanaba Mill:

 

#11 Boiler – September 10 - 23, 2012, 14 days, no manpower as of yet

 

#9 Boiler – September 17 - 21, 2012, five days, no manpower as of yet

 

Kraft Mill – October 22 - 28, 2012 , seven days, no manpower as of yet

Verso Paper Bark Boiler:  The job is complete.  It came in about 4 - 6 days early.  Thanks to all of our members for the outstanding job!

(back to top)

Work in other locals: